Kingston Pike Greenway Connector

Project Description:  

The Town of Farragut, in cooperation with the Tennessee Department of Transportation, is constructing a greenway connector along the Kingston Pike corridor from Old Stage Road to Virtue Road. This section will complete the missing link of pedestrian access from Campbell Station Road to Watt Road via Old Stage Road.

Project Designer:

Cannon & Cannon, Inc.

Construction Contractor:


Contract Amount:


Project Schedule:

Bid Opening: TBD
Notice to Proceed: TBD
Contract Completion Date: TBD


 Engineering Department (865) 966-7057

Status as of 10/1/2016:

The NEPA environmental documents are being reviewed and awaiting approval from the Tennessee DOT. Right of Way phase and final construction plans are underway.